Check the next trade’s release
Interior close-in waits for exterior doors and windows plus HVAC, plumbing, electrical and fire protection rough-in. A completed trade alone does not release the next phase.
Turn a construction project brief into a first schedule draft, then review the WBS, durations, dependencies, resources, and critical path logic in an editable Gantt workspace.
Follow the handoffs from permits to final acceptance, then open the same task structure in the workspace.
This illustrative building schedule uses the same 40 task rows and 56 dependencies as our editable construction template. Its 149-day result is calculated from those tasks. It is a reference for reviewing an AI draft; generated schedules will vary with your brief.
| Project phase | Calendar days from project start | Days |
|---|---|---|
| Preconstruction and Permits | Day 1 to day 9. 3 tasks. | 1–9 |
| Procurement and Mobilization | Day 8 to day 17. 2 tasks. | 8–17 |
| Site Preparation | Day 15 to day 34. 4 tasks. | 15–34 |
| Substructure | Day 35 to day 60. 4 tasks. | 35–60 |
| Superstructure | Day 61 to day 90. 4 tasks. | 61–90 |
| Building Envelope | Day 79 to day 100. 3 tasks. | 79–100 |
| MEP Rough-in | Day 79 to day 95. 5 tasks. | 79–95 |
| Interior Works | Day 101 to day 128. 5 tasks. | 101–128 |
| External Works | Day 61 to day 78. 2 tasks. | 61–78 |
| Testing and Inspections | Day 96 to day 135. 3 tasks. | 96–135 |
| Handover and Closeout | Day 106 to day 149. 5 tasks. | 106–149 |
Phase bars summarize the task dependencies. Tasks within a phase may overlap. Day 1 is your project start.
Assumptions: calendar days, finish-to-start links, zero lag and no resource leveling. Permitting, lead times, curing and inspection durations are example inputs to confirm for your project. Phase bars overlap and should not be added together.
| ID | Task | Days | Predecessor IDs |
|---|---|---|---|
| 4 | Release long-lead materials and subcontract packages | 8–17 | 2 |
| 12 | Foundation concrete pour and curing | 49–60 | 11 |
| 14 | Structural frame erection | 61–78 | 12, 4 |
| 26 | Insulation and drywall close-in | 101–112 | 20, 22, 23, 24, 25 |
| 35 | Authority inspections and approvals | 129–135 | 30, 31, 34 |
| 40 | Final acceptance and project handover | 148–149 | 39 |
You can preview the example before saving. Sign in to save your own plan.
Interior close-in waits for exterior doors and windows plus HVAC, plumbing, electrical and fire protection rough-in. A completed trade alone does not release the next phase.
In this example, adding five days to foundation pouring and curing moves the finish to day 154. The same extension to documentation leaves it at day 149.
The reference uses calendar days without resource leveling. Check working days, delivery commitments, crew availability and inspection requirements before fixing a baseline.
See the calculations and review steps in the construction project timeline guide, or explore another scenario in the delay impact calculator.
Start with the project type, major phases, site constraints, handover target, and any known dates or procurement limits.
Use AI to move from a plain-language brief into task groups, example durations, dependencies, milestones, and review points.
Inspect the generated schedule before using it: check critical tasks, missing dependencies, resource pressure, and unrealistic overlaps.
The generated plan is only as good as the project context. Add field constraints and milestone assumptions before relying on the schedule.
Include this information when it affects sequence, duration, resources, or handover.
Include this information when it affects sequence, duration, resources, or handover.
Include this information when it affects sequence, duration, resources, or handover.
Include this information when it affects sequence, duration, resources, or handover.
Include this information when it affects sequence, duration, resources, or handover.
Include this information when it affects sequence, duration, resources, or handover.
Include this information when it affects sequence, duration, resources, or handover.
Include this information when it affects sequence, duration, resources, or handover.
A useful construction schedule generator should create a connected plan that a planner can interrogate, not a static checklist.
Use AI for the first pass when you do not want to start from a blank task list.
Generated schedules should become normal project plans that can be edited, saved, and reviewed.
A useful construction generator needs dependency logic, not only a list of phase names.
The worked example is an illustrative construction template with 40 task rows and calculated dependencies. It is a reference for reviewing a draft, not a fixed AI response. Your output depends on the project brief; confirm scope, calendars, durations and handoffs before using it.
AI can create a practical first draft, but it should not be treated as a final baseline. Review scope, durations, dependencies, resources, procurement, permits, inspections, and handover constraints before using the plan.
Provide the project type, major deliverables, known start or finish dates, long-lead items, site constraints, crew assumptions, and any milestones that cannot move.
Yes. A template starts from a fixed structure. An AI construction schedule generator starts from your brief and drafts a schedule that still needs planner review.
Yes. The intended workflow is to generate a draft, review it as a Gantt chart, then edit tasks, dates, dependencies, resources, and milestones.