Join delivery and civil readiness before the lift
Task 13 waits for the approved lifting arrangements, receiving inspection and foundation release. A finished foundation alone does not mean the equipment can be set.
Free equipment installation schedule template for Excel and CSV: 33 linked tasks from delivery and foundations to commissioning. Preview and edit online.
Free downloads and page preview, no signup. 33 tasks, 8 phases, linked dates and dependencies. Choose a start date to create your own editable plan, then refine it with AI. Sign in if needed.
| Project phase | Calendar days from project start | Days |
|---|---|---|
| Planning and Engineering | Day 1 to day 9. 4 tasks. | 1–9 |
| Delivery and Receiving | Day 7 to day 26. 3 tasks. | 7–26 |
| Site and Foundation Readiness | Day 7 to day 24. 5 tasks. | 7–24 |
| Lifting and Setting | Day 27 to day 37. 5 tasks. | 27–37 |
| Mechanical Completion | Day 38 to day 43. 3 tasks. | 38–43 |
| Electrical and Controls | Day 9 to day 45. 5 tasks. | 9–45 |
| Commissioning and Acceptance | Day 46 to day 52. 4 tasks. | 46–52 |
| Handover | Day 44 to day 55. 4 tasks. | 44–55 |
Phase bars summarize the task dependencies. Tasks within a phase may overlap. Day 1 is your project start.
The sample spans 55 calendar days. Receiving inspection and foundation release both feed lift readiness. Vendor lead times, concrete and grout releases, and the commissioning scope determine whether these sample dates fit your equipment package.
All links are finish-to-start with no lag. The preview and workbook use calendar days including weekends, an 8-hour example workday and no holidays. Approval and handover reviews are one-day activities. The dependency calculation does not level crews or equipment. Set your actual calendar, resources and hold points before agreeing to a baseline.
The CSV contains the same task IDs, durations, predecessors and resource names as the page. It is a task list; the Excel workbook also includes calculated dates and a weekly Gantt view. For online editing,open this template or import a modified spreadsheet.
Inspect the tasks before downloading. Day numbers below are calculated from the predecessor links; they start at day 1.
| ID | Phase | Task | Days | Depends on | Start–finish | Resources |
|---|---|---|---|---|---|---|
| 1 | Planning and Engineering | Confirm equipment scope and installation boundaries | 2 | — | 1–2 | Project manager |
| 2 | Planning and Engineering | Review vendor drawings and interface requirements | 4 | 1 | 3–6 | Design team |
| 3 | Planning and Engineering | Confirm utility loads and connection points | 2 | 2 | 7–8 | Design team |
| 4 | Planning and Engineering | Approve lifting plan and access arrangements | 3 | 2 | 7–9 | Project manager |
| 5 | Delivery and Receiving | Release purchase order and vendor documents | 3 | 2 | 7–9 | Procurement team |
| 6 | Delivery and Receiving | Manufacture and dispatch equipment | 15 | 5 | 10–24 | Procurement team |
| 7 | Delivery and Receiving | Receive equipment and close receiving inspection | 2 | 6 | 25–26 | Inspection team |
| 8 | Site and Foundation Readiness | Survey equipment location and foundation setting out | 2 | 2 | 7–8 | Civil crew |
| 9 | Site and Foundation Readiness | Construct equipment foundations and embedded items | 5 | 8 | 9–13 | Concrete crew |
| 10 | Site and Foundation Readiness | Allow foundation curing and strength verification | 10 | 9 | 14–23 | Civil crew |
| 11 | Site and Foundation Readiness | Release foundation survey and civil handover | 1 | 10 | 24–24 | Inspection team |
| 12 | Site and Foundation Readiness | Prepare utility connections and workface access | 4 | 3 | 9–12 | Civil crew |
| 13 | Lifting and Setting | Confirm equipment, foundation and lift readiness | 1 | 4, 7, 11 | 27–27 | Project manager, Inspection team |
| 14 | Lifting and Setting | Lift and position equipment | 2 | 13 | 28–29 | Mechanical installation crew, Mobile crane |
| 15 | Lifting and Setting | Align and level equipment | 2 | 14 | 30–31 | Mechanical installation crew |
| 16 | Lifting and Setting | Complete equipment base grouting | 3 | 15 | 32–34 | Concrete crew |
| 17 | Lifting and Setting | Verify grout release for connected work | 3 | 16 | 35–37 | Inspection team |
| 18 | Mechanical Completion | Connect piping and mechanical services | 3 | 12, 17 | 38–40 | Mechanical installation crew |
| 19 | Mechanical Completion | Complete guards, lubrication and mechanical checks | 2 | 18 | 41–42 | Mechanical installation crew |
| 20 | Mechanical Completion | Review mechanical completion and outstanding items | 1 | 19 | 43–43 | Inspection team |
| 21 | Electrical and Controls | Install cable routes and equipment cabling | 4 | 12, 14 | 30–33 | Electrical crew |
| 22 | Electrical and Controls | Terminate power and control cables | 3 | 21 | 34–36 | Electrical crew |
| 23 | Electrical and Controls | Complete de-energized electrical test records | 2 | 22 | 37–38 | Electrical crew, Inspection team |
| 24 | Electrical and Controls | Configure controls and approved operating sequence | 3 | 3 | 9–11 | Commissioning engineers |
| 25 | Electrical and Controls | Complete loop and interlock verification | 2 | 20, 23, 24 | 44–45 | Electrical crew, Commissioning engineers |
| 26 | Commissioning and Acceptance | Approve readiness for energization and testing | 1 | 20, 25 | 46–46 | Project manager, Inspection team |
| 27 | Commissioning and Acceptance | Run no-load commissioning tests | 2 | 26 | 47–48 | Commissioning engineers |
| 28 | Commissioning and Acceptance | Run loaded trials and record performance | 3 | 27 | 49–51 | Commissioning engineers |
| 29 | Commissioning and Acceptance | Review performance acceptance results | 1 | 28 | 52–52 | Inspection team |
| 30 | Handover | Close handover-critical punch items | 2 | 29 | 53–54 | Mechanical installation crew |
| 31 | Handover | Compile as-built and commissioning records | 3 | 20 | 44–46 | Project manager |
| 32 | Handover | Train operators and maintenance personnel | 2 | 28 | 52–53 | Commissioning engineers |
| 33 | Handover | Complete final equipment handover review | 1 | 30, 31, 32 | 55–55 | Project manager, Inspection team |
| Phase | Included work | Planning purpose |
|---|---|---|
| Planning and Engineering | Scope, vendor drawings, utility interfaces, lifting approvals | Confirm equipment interfaces before ordering, preparing foundations or reserving lifting access. |
| Delivery and Receiving | Purchase release, manufacture and dispatch, receiving inspection | Physical delivery and receipt acceptance are separate from civil progress. Replace the sample lead time with the vendor commitment. |
| Site and Foundation Readiness | Setting out, foundation works, curing allowance, survey release, utilities | Setting requires released foundations and access. Concrete strength and survey acceptance need project-specific approval. |
| Lifting and Setting | Lift readiness, positioning, alignment, grouting and release | Receiving, foundations and lift readiness join before setting. The grout release is a distinct hold point. |
| Mechanical Completion | Service connections, guards, lubrication, mechanical completion review | Mechanical completion provides a checkable boundary before integrated controls testing. |
| Electrical and Controls | Cabling, termination, de-energized testing, controls setup, loop checks | Cable installation can overlap mechanical work, while final loop and interlock checks wait for the required interfaces. |
| Commissioning and Acceptance | Energization release, no-load testing, loaded trials, acceptance review | Separate readiness approval from the test period and the acceptance decision. |
| Handover | Critical punch items, records, training, final handover review | Documentation can develop in parallel. Final handover still waits for required defects and training to be closed. |
Task 13 waits for the approved lifting arrangements, receiving inspection and foundation release. A finished foundation alone does not mean the equipment can be set.
Tasks 10 and 17 are example allowances. Replace them with the specified material, strength evidence and engineer or vendor release requirements; these durations are not curing instructions.
Cable routes and controls setup run on separate branches. Task 25 waits for mechanical completion, electrical records and controls configuration.
Performance review, critical punch closure, operating training and records each have an owner and a dependency before final handover.
Review the impact of schedule changes, then save, reopen and check the output before sharing the plan. Editing and export access depend on your GanttPilot plan.
The Excel and CSV downloads and page preview are free without signup. Sign in to preview the same template in GanttPilot, then apply it to your own plan to edit and save. Editing and export access depend on your plan.
Yes. Change the project start in B4, durations in column D and earlier predecessor IDs in E–I. Start and finish dates and the weekly Gantt chart recalculate. The workbook uses calendar days including weekends; it does not exclude holidays.
Yes, as a starting task structure. Replace foundation, lifting, service, controls and test tasks with the requirements for your equipment package.
No. They are illustrative whole-day planning allowances. Confirm vendor delivery, strength release, crew productivity and acceptance requirements before setting a baseline.
It focuses on an equipment package and its interfaces. Use the construction or aggregate processing plant template when buildings, major civil works and multiple process areas also need to be planned.