| 1.1 | Project charter and scope baseline | 3 days | - | Project manager |
| 1.2 | Build work breakdown structure and schedule baseline | 4 days | 1 | Project manager |
| 1.3 | Confirm milestones and reporting calendar | 2 days | 2 | Project manager |
| 2.1 | Basis of design and specifications | 8 days | 2 | Design team |
| 2.2 | Layout and general arrangement drawings | 10 days | 4 | Design team |
| 2.3 | Mechanical and structural detail design | 12 days | 5 | Design team |
| 2.4 | Electrical and control system design | 10 days | 5 | Design team |
| 2.5 | Design review and approval | 5 days | 6, 7 | Design team, Project manager |
| 3.1 | Long-lead equipment inquiry and bid review | 10 days | 4 | Procurement team |
| 3.2 | Purchase orders for major equipment | 5 days | 9 | Procurement team |
| 3.3 | Equipment manufacturing and delivery | 45 days | 10 | Procurement team |
| 3.4 | Bulk materials and consumables | 20 days | 8 | Procurement team |
| 3.5 | Subcontract award and mobilization | 8 days | 8 | Procurement team |
| 4.1 | Site survey and setting out | 3 days | 13 | Civil crew |
| 4.2 | Excavation and subgrade preparation | 8 days | 14 | Civil crew |
| 4.3 | Equipment foundations and anchor bolts | 14 days | 6, 15 | Civil crew |
| 4.4 | Foundation curing and survey check | 10 days | 16 | Civil crew, Inspection team |
| 5.1 | Equipment receiving and inspection | 4 days | 11 | Mechanical installation crew, Inspection team |
| 5.2 | Setting main equipment | 12 days | 17, 18 | Mechanical installation crew, Mobile crane |
| 5.3 | Alignment and grouting | 8 days | 19 | Mechanical installation crew |
| 5.4 | Piping and utilities connection | 14 days | 12, 19 | Mechanical installation crew |
| 5.5 | Mechanical completion walkdown | 4 days | 20, 21 | Inspection team |
| 6.1 | Cable tray, conduit, and cabling | 12 days | 7, 19 | Electrical crew |
| 6.2 | Panel and MCC installation | 8 days | 23 | Electrical crew |
| 6.3 | Instrument installation and loop wiring | 10 days | 24 | Electrical crew |
| 6.4 | Loop checks and point-to-point testing | 8 days | 22, 25 | Electrical crew, Commissioning engineers |
| 7.1 | No-load and cold commissioning | 8 days | 26 | Commissioning engineers |
| 7.2 | Load testing and performance run | 10 days | 27 | Commissioning engineers |
| 7.3 | Punch list walkdown and closeout | 6 days | 28 | Inspection team, Project manager |
| 7.4 | As-built drawings and O&M manuals | 6 days | 28 | Design team |
| 7.5 | Training and final handover | 4 days | 29, 30 | Commissioning engineers, Project manager |