Schedule template

Aggregate Processing Plant Construction Schedule Template

Download a CSV schedule template for an aggregate processing plant project, preview the Gantt chart, or open the template in GanttPilot to edit tasks and dependencies online.

Includes 9 phases, 34 tasks, dependencies, commissioning, and handover rows. Use it as a starting point, not a final baseline.

Template task table

Review the full task list before downloading. The CSV file uses these same rows, including phase names, durations, and dependency references.

PhaseTaskDurationDepends on
Project PreparationProject kickoff and schedule baseline2 days-
Project PreparationReview process flow and layout drawings5 days1
Project PreparationConfirm equipment delivery schedule3 days1
Site PreparationSite survey and setting out4 days2
Site PreparationTemporary access road preparation7 days4
Civil WorksPrimary crushing station foundation8 days5
Civil WorksScreening workshop foundation8 days5
Civil WorksTransfer tower and conveyor foundations10 days5
Civil WorksConcrete pouring and curing14 days6, 7, 8
Steel StructureSteel structure material delivery3 days3
Steel StructureScreening workshop steel structure10 days9, 10
Steel StructurePrimary crushing station steel platform6 days9, 10
Equipment InstallationJaw crusher installation5 days9
Equipment InstallationCone crusher installation5 days9
Equipment InstallationVibrating screen installation6 days11
Equipment InstallationFeeder and chute installation5 days12, 13
Conveyor SystemTransfer tower installation6 days8, 11
Conveyor SystemBelt conveyor support installation8 days8
Conveyor SystemBelt conveyor mechanical installation10 days18
Conveyor SystemBelt scale and metal detector installation4 days19
UtilitiesDust collection system installation7 days11, 17
UtilitiesWater supply and drainage connection6 days9
Electrical and ControlsMCC cabinet and control room setup6 days11
Electrical and ControlsCable tray installation7 days11, 17
Electrical and ControlsMotor cabling and termination10 days23, 24
Electrical and ControlsPLC and HMI control system setup7 days23
Electrical and ControlsInstrument and safety interlock wiring6 days25, 26
CommissioningSingle equipment dry run6 days13, 14, 15, 25
CommissioningConveyor no-load integrated test5 days19, 20, 25
CommissioningSystem interlock test5 days26, 27, 28, 29
CommissioningLoaded trial run7 days30
CommissioningProduct gradation adjustment5 days31
HandoverPerformance test and capacity verification5 days32
HandoverPunch list correction and final handover5 days33

What is included in the schedule structure

Each phase exists for a reason. The template separates civil readiness, steel access, process equipment, conveyors, electrical controls, commissioning, and handover so you can adjust the plan without losing the construction logic.

WBSPhaseTypical tasksWhy it mattersDuration
1Project PreparationContract kickoff, design review, procurement planning, schedule baselineLocks the process flow, layout assumptions, and long-lead equipment plan before field work starts.5-10 days
2Site PreparationSurvey, clearing, access road, temporary power, temporary facilitiesCreates safe access and temporary utilities for concrete, steel erection, equipment delivery, and lifting work.10-20 days
3Civil WorksExcavation, equipment foundations, retaining walls, drainage, concrete curingCrusher, screen, conveyor, and transfer tower installation cannot start reliably until foundations are ready.25-40 days
4Steel StructureColumn installation, platforms, stairs, handrails, chute supportsPlatforms and supports define access, chute interfaces, and the workface for mechanical installation.15-25 days
5Equipment InstallationJaw crusher, cone crusher, vibrating screens, feedersMajor process equipment sets the mechanical path that conveyors, cabling, and testing must follow.20-35 days
6Conveyor SystemBelt conveyor supports, pulleys, belts, drives, guards, transfer pointsConveyors connect the process line; no-load and loaded tests depend on stable transfer points.15-30 days
7Electrical and ControlsCable trays, MCC panels, motor wiring, sensors, PLC cabinets, control roomMotors, sensors, interlocks, and PLC controls must be ready before integrated commissioning.20-35 days
8CommissioningDry run, single machine test, interlock test, load test, dust and water system checksThe plant must prove single-equipment, no-load, interlock, and loaded operation before acceptance.10-20 days
9HandoverPunch list, training, documentation, acceptance, final handoverFinal records, training, punch list closure, and performance acceptance turn the schedule into a deliverable plan.5-10 days

Why this schedule is structured this way

The template is not only a task list. It reflects the construction logic behind aggregate processing plants: foundations, access steel, process equipment, conveyors, controls, and commissioning all constrain each other.

Why the template separates civil, steel, and equipment work

Aggregate plants look like equipment projects, but installation quality depends heavily on foundation readiness, access platforms, transfer points, and chute interfaces.

Why conveyors appear as their own phase

A plant may have several crushers and screens, but material flow depends on conveyors, pulleys, drives, guards, belts, belt scales, and transfer points working together.

Why commissioning is not a single final task

Single equipment dry run, conveyor no-load test, interlock test, loaded trial run, product gradation adjustment, and performance verification are different checks.

Key dependencies to review

Before you use the template as a baseline, review these dependency groups. They are common schedule drivers in fixed crushing, screening, and sand-and-gravel processing projects.

Civil foundations drive the installation start

Crusher foundations, screening workshop foundations, and transfer tower foundations must be complete and cured before most mechanical work can start.

Steel structure controls access and transfer points

Platforms, supports, handrails, chutes, and transfer towers define where screens, feeders, conveyors, and dust systems can be installed.

Electrical and controls are commissioning prerequisites

Motor cabling, MCC setup, PLC/HMI configuration, instruments, and safety interlocks must be ready before integrated no-load and loaded tests.

Loaded trial run comes before product adjustment

Gradation adjustment and performance verification should happen after the plant has passed interlock checks and loaded trial operation.

Resource and cost notesResource peaks usually appear before commissioning, not only at handover.
  • Civil crew demand peaks around foundation excavation, reinforcement, pouring, and curing coordination.
  • Crane and mechanical crew availability can constrain crusher, screen, feeder, and transfer tower installation.
  • Electrical crew demand usually peaks when cable trays, motor cabling, terminations, PLC work, and instruments overlap.
  • Commissioning engineers, operations staff, and maintenance staff should be reserved before no-load and loaded trial runs.

How to customize this template

Use the CSV as a planning worksheet, or open the Gantt version in GanttPilot and adjust the dates, task names, durations, dependencies, resources, and milestones to match your actual project.

  • Update the plant capacity, process flow, and equipment list.
  • Adjust civil foundation work around site conditions and curing time.
  • Connect delivery, installation, cabling, commissioning, and handover tasks.
  • Use the Gantt view to inspect downstream impact when dates move.
Template workflowAdjust the template only after checking scope, delivery dates, access, and commissioning constraints.

When the sequence changes, review downstream tasks such as conveyor installation, motor cabling, interlock testing, loaded trial run, and final handover. These are where small date changes often create real schedule pressure.

Common questions

What is included in this aggregate processing plant schedule template?

The template includes preparation, site work, civil foundations, steel structure, equipment installation, conveyors, electrical and controls, commissioning, loaded trial run, product adjustment, performance test, and handover tasks.

Can I download the schedule template?

Yes. The CSV download includes the sample task list, phase labels, durations, and dependencies shown on this page.

Can I open this template in GanttPilot?

Yes. The Open in GanttPilot action loads the aggregate processing plant schedule as an editable Gantt project.

Can I use this template for a sand and gravel plant?

Yes. It can be adapted for sand and gravel processing plants, quarry crushing lines, manufactured sand systems, and fixed aggregate production facilities.

What dependencies affect crusher and conveyor installation?

Civil foundations, concrete curing, steel supports, transfer towers, equipment delivery, and electrical readiness are the main dependency groups to review.

How long does aggregate plant commissioning take?

The example allows 10-20 days for commissioning, but the actual duration depends on equipment count, interlock complexity, loaded trial results, and product gradation adjustment.

Is this a finished project schedule?

No. It is a starting template. Review task scope, durations, resources, delivery dates, site access, and commissioning requirements before using it as a baseline schedule.