Why the template separates civil, steel, and equipment work
Aggregate plants look like equipment projects, but installation quality depends heavily on foundation readiness, access platforms, transfer points, and chute interfaces.
Download a CSV schedule template for an aggregate processing plant project, preview the Gantt chart, or open the template in GanttPilot to edit tasks and dependencies online.
Includes 9 phases, 34 tasks, dependencies, commissioning, and handover rows. Use it as a starting point, not a final baseline.
Review the full task list before downloading. The CSV file uses these same rows, including phase names, durations, and dependency references.
| Phase | Task | Duration | Depends on |
|---|---|---|---|
| Project Preparation | Project kickoff and schedule baseline | 2 days | - |
| Project Preparation | Review process flow and layout drawings | 5 days | 1 |
| Project Preparation | Confirm equipment delivery schedule | 3 days | 1 |
| Site Preparation | Site survey and setting out | 4 days | 2 |
| Site Preparation | Temporary access road preparation | 7 days | 4 |
| Civil Works | Primary crushing station foundation | 8 days | 5 |
| Civil Works | Screening workshop foundation | 8 days | 5 |
| Civil Works | Transfer tower and conveyor foundations | 10 days | 5 |
| Civil Works | Concrete pouring and curing | 14 days | 6, 7, 8 |
| Steel Structure | Steel structure material delivery | 3 days | 3 |
| Steel Structure | Screening workshop steel structure | 10 days | 9, 10 |
| Steel Structure | Primary crushing station steel platform | 6 days | 9, 10 |
| Equipment Installation | Jaw crusher installation | 5 days | 9 |
| Equipment Installation | Cone crusher installation | 5 days | 9 |
| Equipment Installation | Vibrating screen installation | 6 days | 11 |
| Equipment Installation | Feeder and chute installation | 5 days | 12, 13 |
| Conveyor System | Transfer tower installation | 6 days | 8, 11 |
| Conveyor System | Belt conveyor support installation | 8 days | 8 |
| Conveyor System | Belt conveyor mechanical installation | 10 days | 18 |
| Conveyor System | Belt scale and metal detector installation | 4 days | 19 |
| Utilities | Dust collection system installation | 7 days | 11, 17 |
| Utilities | Water supply and drainage connection | 6 days | 9 |
| Electrical and Controls | MCC cabinet and control room setup | 6 days | 11 |
| Electrical and Controls | Cable tray installation | 7 days | 11, 17 |
| Electrical and Controls | Motor cabling and termination | 10 days | 23, 24 |
| Electrical and Controls | PLC and HMI control system setup | 7 days | 23 |
| Electrical and Controls | Instrument and safety interlock wiring | 6 days | 25, 26 |
| Commissioning | Single equipment dry run | 6 days | 13, 14, 15, 25 |
| Commissioning | Conveyor no-load integrated test | 5 days | 19, 20, 25 |
| Commissioning | System interlock test | 5 days | 26, 27, 28, 29 |
| Commissioning | Loaded trial run | 7 days | 30 |
| Commissioning | Product gradation adjustment | 5 days | 31 |
| Handover | Performance test and capacity verification | 5 days | 32 |
| Handover | Punch list correction and final handover | 5 days | 33 |
Each phase exists for a reason. The template separates civil readiness, steel access, process equipment, conveyors, electrical controls, commissioning, and handover so you can adjust the plan without losing the construction logic.
| WBS | Phase | Typical tasks | Why it matters | Duration |
|---|---|---|---|---|
| 1 | Project Preparation | Contract kickoff, design review, procurement planning, schedule baseline | Locks the process flow, layout assumptions, and long-lead equipment plan before field work starts. | 5-10 days |
| 2 | Site Preparation | Survey, clearing, access road, temporary power, temporary facilities | Creates safe access and temporary utilities for concrete, steel erection, equipment delivery, and lifting work. | 10-20 days |
| 3 | Civil Works | Excavation, equipment foundations, retaining walls, drainage, concrete curing | Crusher, screen, conveyor, and transfer tower installation cannot start reliably until foundations are ready. | 25-40 days |
| 4 | Steel Structure | Column installation, platforms, stairs, handrails, chute supports | Platforms and supports define access, chute interfaces, and the workface for mechanical installation. | 15-25 days |
| 5 | Equipment Installation | Jaw crusher, cone crusher, vibrating screens, feeders | Major process equipment sets the mechanical path that conveyors, cabling, and testing must follow. | 20-35 days |
| 6 | Conveyor System | Belt conveyor supports, pulleys, belts, drives, guards, transfer points | Conveyors connect the process line; no-load and loaded tests depend on stable transfer points. | 15-30 days |
| 7 | Electrical and Controls | Cable trays, MCC panels, motor wiring, sensors, PLC cabinets, control room | Motors, sensors, interlocks, and PLC controls must be ready before integrated commissioning. | 20-35 days |
| 8 | Commissioning | Dry run, single machine test, interlock test, load test, dust and water system checks | The plant must prove single-equipment, no-load, interlock, and loaded operation before acceptance. | 10-20 days |
| 9 | Handover | Punch list, training, documentation, acceptance, final handover | Final records, training, punch list closure, and performance acceptance turn the schedule into a deliverable plan. | 5-10 days |
The template is not only a task list. It reflects the construction logic behind aggregate processing plants: foundations, access steel, process equipment, conveyors, controls, and commissioning all constrain each other.
Aggregate plants look like equipment projects, but installation quality depends heavily on foundation readiness, access platforms, transfer points, and chute interfaces.
A plant may have several crushers and screens, but material flow depends on conveyors, pulleys, drives, guards, belts, belt scales, and transfer points working together.
Single equipment dry run, conveyor no-load test, interlock test, loaded trial run, product gradation adjustment, and performance verification are different checks.
Before you use the template as a baseline, review these dependency groups. They are common schedule drivers in fixed crushing, screening, and sand-and-gravel processing projects.
Crusher foundations, screening workshop foundations, and transfer tower foundations must be complete and cured before most mechanical work can start.
Platforms, supports, handrails, chutes, and transfer towers define where screens, feeders, conveyors, and dust systems can be installed.
Motor cabling, MCC setup, PLC/HMI configuration, instruments, and safety interlocks must be ready before integrated no-load and loaded tests.
Gradation adjustment and performance verification should happen after the plant has passed interlock checks and loaded trial operation.
Use the CSV as a planning worksheet, or open the Gantt version in GanttPilot and adjust the dates, task names, durations, dependencies, resources, and milestones to match your actual project.
When the sequence changes, review downstream tasks such as conveyor installation, motor cabling, interlock testing, loaded trial run, and final handover. These are where small date changes often create real schedule pressure.
The template includes preparation, site work, civil foundations, steel structure, equipment installation, conveyors, electrical and controls, commissioning, loaded trial run, product adjustment, performance test, and handover tasks.
Yes. The CSV download includes the sample task list, phase labels, durations, and dependencies shown on this page.
Yes. The Open in GanttPilot action loads the aggregate processing plant schedule as an editable Gantt project.
Yes. It can be adapted for sand and gravel processing plants, quarry crushing lines, manufactured sand systems, and fixed aggregate production facilities.
Civil foundations, concrete curing, steel supports, transfer towers, equipment delivery, and electrical readiness are the main dependency groups to review.
The example allows 10-20 days for commissioning, but the actual duration depends on equipment count, interlock complexity, loaded trial results, and product gradation adjustment.
No. It is a starting template. Review task scope, durations, resources, delivery dates, site access, and commissioning requirements before using it as a baseline schedule.